Clarence Valley Councillor Debrah Novak called the Yamba Community Precinct project update item at this month’s ordinary meeting to let residents know about a walk through that the Councillors took part of.
“We had a great walk through here not so long ago it looked absolutely brilliant. Very very exciting. A piece of brand-new infrastructure for Yamba.
“It’s a great asset to be alongside the TAFE digital learning centre. I look forward to the opening in the middle of the year.
“I’m really happy our young people will be able to be welcomed and use the facility as a new home to be at.”
As of January, several key milestones have been achieved, bringing us closer to completion with the project running on-track to be delivered on time to be completed by May 2025.
Painting works are well advanced throughout the building, enhancing the aesthetic appeal and finalising interior finishes. The installation of joinery is progressing steadily, with the northern half of the building already completed. Work has commenced on installing operable walls to effectively divide meeting rooms, ensuring flexible and functional spaces. All tiling works have been completed, alongside the successful installation of hydraulic systems in bathrooms, ensuring fully operational facilities.
All aluminium doors, windows, and louvres have been installed, securing the building and providing the necessary ventilation and natural light. The completion of inground hydraulic service works marks a crucial step in ensuring a robust plumbing and drainage system. All necessary electrical upgrades have been successfully carried out, providing enhanced power capacity and reliability.
Landscaping works have commenced, contributing to the visual appeal and environmental sustainability of the project. The carpark pavement has been completed, along with the necessary electrical installations, ensuring accessibility and functionality for future users.
With these key activities completed, the focus now shifts to finalizing remaining interior works, landscaping, and other finishing touches. The project remains on track for timely completion, and further updates will be provided as progress continues.
Source: CVC Communications