Work to improve the Villiers street roundabout in Grafton has begun, marking another important step towards the opening of the new Grafton Bridge.
Transport for NSW Regional Director Northern Anna Andrews said the work at the intersection of Villiers and Pound Streets would extend the life of the existing roundabout.
“In order to carry out the work safely and efficiently, this intersection will be reduced to one lane in either direction to maintain the large volume of traffic on Villiers Street,” Ms Andrews said.
“Vegetation in the middle of the existing roundabout has been removed and temporary road pavement is being laid.
“The next step is for sections of the existing concrete roundabout to be removed and replaced, and the road pavement widened.
“The work to replace sections of the roundabout will then be carried out in stages.
“Some detours will be required for heavy and light vehicles while work is completed.”
The traffic arrangement for Stage 1 of the work (see map) will be put into place this week, with residents and motorists to be informed before Stage 2 starts.
Local businesses, TAFE and Grafton Shoppingworld have been consulted about the need to carry out this roundabout upgrade.
Work is expected to take about eight weeks to complete, weather permitting.
Villiers Street will become part of the Summerland Way when the new Grafton Bridge opens to traffic.
Traffic control and a reduced speed limit will be in place for the safety of workers and motorists.