Changed traffic conditions for the Woolgoolga to Ballina upgrade

Motorists are advised of changed traffic conditions on the Pacific Highway and local roads from Monday 5 to Sunday 11 July for the Woolgoolga to Ballina upgrade, weather permitting.

 

There will be no roadwork on the Pacific Highway between Kew and the Queensland border from 6am Friday 9 July to 6am Monday 12 July due to the traffic volume expected for the school holidays. 

 

From Monday, there will be four days of work on the Pacific Highway between the new bridge over the Richmond River and Broadwater interchange to carry out pavement maintenance. Motorists can expect lane closures, traffic control and a reduced speed limit at times between 6am and 6pm.

 

Also from Monday, there will be up to four days of work on the Pacific Highway between Woodburn and Devils Pulpit to carry out maintenance and finishing work. Motorists can expect lane closures, traffic control and a reduced speed limit at times between 6am and 6pm.

 

Further south from Monday, there will be up to four days of work on the Pacific Highway between the Iluka and Maclean interchanges to carry out pavement maintenance. Motorists can expect lane closures, traffic control and a reduced speed limit at times between 6am and 6pm.

 

On Thursday, there will be one day of work on the Pacific Highway close to the Pine Brush Rest Areas at Tucabia to carry out survey monitoring. Motorists can expect lane closures, traffic control and a reduced speed limit at times between 6am and 6pm.

 

Additional changes to local roads

 

From Monday, there will be up to three days of work on Rifle Range Road at Broadwater to install fencing. Motorists can expect lane closures, traffic control and a reduced speed limit at times between 6am and 6pm between 6am and 6pm.

 

Also from Monday, there will be up to five days of work on Woodburn Evans Head Road at Woodburn and the former Pacific Highway near the Woodburn interchange to carry out survey monitoring, private access work and maintenance. Motorists can expect lane and shoulder closures and traffic control at times between 6am and 6pm.

 

Further south from Monday, there will be up to five days of work on Swan Bay New Italy, Marozin and Nardi roads at New Italy to carry out private access and finishing work. Motorists can expect lane closures and traffic control at times between 6am and 6pm.

 

On Tuesday, there will be one day of work at the Coolgardie interchange to carry out maintenance. Motorists can expect lane closures, traffic control and reduced speed limit at times between 6am and 6pm.

 

For the latest traffic updates download the Live Traffic NSW App, visit livetraffic.com or call 132 701.